What is a normal change?
-
A
A change that doesn’t need risk assessment because the procedure has been preauthorized
-
B
A change that needs to be assessed, authorized, and scheduled by a change authority
-
C
A change that doesn’t need risk assessment because it is required to resolve an incident
-
D
A change that is routine in nature, is fully documented, and the risks are well understood